Hexi Pod 1

The full specification.

Everything that's in Pod 1, and everything that isn't. Figures are confirmed for your site during the reservation.

Capacity
Seven customer-supplied NVIDIA GB300 NVL72 racks (504 GPUs), plus three or four support racks. Total IT envelope 1.05 MW, about 140 kW per GPU rack. A 0.5 MW option on the same design can be priced.
Structure
Purpose-built transportable modules: a separate power room, IT modules and an external cooling compound. Final module count follows weight, access and service clearances.
Site
A plot of about 400 to 800 m² including coolers, power equipment, crane access, maintenance space and fire access. Confirmed in the reservation survey.
Power
About 1.5 MVA of firm, usable spare import at the agreed boundary. Preferably an existing 11 kV connection and transformer; otherwise one 2 MVA 11 kV to 400/415 V transformer.
Electrical resilience
One utility source and one transformer. A and B rack distribution where supported. Modular UPS with N+1 power modules and maintenance bypass. The upstream supply remains a single point of failure.
UPS
About 1.2 MW usable UPS capacity with about five minutes of autonomy at design load, supporting coolant units, controls and safe shutdown.
Liquid cooling
Direct-to-chip cooling through isolated facility and technology loops. Indicatively three 600 kW coolant distribution units, any two able to carry the duty.
Heat rejection
Sized for the full IT and plant heat balance. Dry coolers with adiabatic or mechanical trim where needed, checked at summer design conditions and at 40°C.
Residual air cooling
A separate air path for up to about 25% of IT heat, with N+1 units, confirmed against your server maker's figures.
Controls
Separate IT and facility metering. Leak detection, coolant chemistry, pressure, flow, temperature, electrical quality and alarms. Open interfaces and remote access you control.
Fire and security
Insurer-approved detection, compartmentation and suppression. Segregated batteries. Secure access, CCTV and alarm escalation.
Acceptance
Factory acceptance tests, site acceptance tests and an integrated load test: load ramps, a cooling-unit failure, leaks, alarms, emergency stops and UPS shutdown.

Not included

  • GPUs, servers and the IT racks supplied with them
  • Cluster networking, storage, software and IT support
  • Land, financing and major utility reinforcement
  • A standby generator, unless separately designed and priced
  • Tier III or fault-tolerant resilience, available as a separate design

Price and timing

£4M to £7M excluding VAT and GPUs, depending on the site. 26 to 40 weeks from order where suitable electrical plant already exists; 52 to 78 weeks if a new transformer and switchgear are needed. These are estimates until the reservation turns them into a firm, partner-backed offer.